30-hour grid supply marks progress
Rooppur Delivers Tk7.06 Crore Worth of Power
- First unit supplies electricity continuously for nearly 30 hours
- Approximately 320 MW delivered to the national grid
- Estimated electricity value reaches Tk7.06 crore
Bangladesh's nuclear power generation programme has recorded another significant operational milestone, with the first unit of the Rooppur Nuclear Power Plant supplying approximately 320 megawatts of electricity to the national grid continuously for nearly 30 hours during its second test run. The electricity delivered during this period is estimated to be worth Tk7.06 crore. The extended supply marks further progress in assessing the plant's operational capability, turbine-generator performance and integration with the national grid.
The electricity supply was discontinued at 5:05 pm on Tuesday, November 24, 2026.
Operated by Nuclear Power Company Bangladesh Limited (NPCBL), the first unit successfully connected to the national grid for the second time and supplied electricity during the latest test.
Multiple sources from the national transmission network said the first unit of Rooppur consistently supplied around 320 MW during this phase.
According to relevant sources, the initial plan was to conduct a test electricity supply lasting between 10 and 24 hours. However, the supply continued for nearly 30 hours, exceeding the planned timeframe.
The estimated financial value of the electricity supplied to the national grid during this period stands at Tk7.06 crore.
The latest achievement is being viewed as an important milestone in Bangladesh's journey towards nuclear power generation. Project-related officials consider it a significant accomplishment for NPCBL in demonstrating the plant's operational capability and technical readiness.
Following the successful second phase of electricity supply, the first unit was disconnected from the national grid.
Various operating parameters recorded during the electricity supply are now being analysed. The assessment also covers the performance of the turbine-generator system and the functionality of associated equipment.
NPCBL said the findings of these analyses would determine the next operational steps.
NPCBL Managing Director Dr Md Jahedul Hasan said, "Successfully connecting to the national grid for the second time and supplying 320 MW of electricity continuously for 30 hours is a matter of great joy and pride for us. This reflects NPCBL's operational capability, the skills of our engineers and operators, and our collective efforts with Russian operational partners."
He further said, "As the plant operator, NPCBL remains committed to the safe, reliable and efficient operation of the facility. We are proceeding with subsequent activities by ensuring the highest standards of nuclear safety and following international standards and regulatory guidelines."
He congratulated the Ministry of Science and Technology, Bangladesh Atomic Energy Commission, Bangladesh Atomic Energy Regulatory Authority, Russian partner organisations, NPCBL officials and employees, and all relevant experts involved in the achievement.
The Rooppur Nuclear Power Plant is designed to generate a combined 2,400 MW of electricity from its two units.
Once both units become fully operational, the plant is expected to play an important role in diversifying Bangladesh's electricity generation mix, reducing dependence on fossil fuels and strengthening long-term energy security.