Rooppur Completes Nuclear Fuel Deliveries

Final Uranium Shipment Reaches Rooppur Unit Two

  • Nine scheduled fuel shipments completed for both units
  • Seven shipments delivered 163 assemblies for Unit Two
  • Unit One continues trial electricity supply

Final Uranium Shipment Reaches Rooppur Unit Two
Nov 27, 2026 08:55

The ninth and final shipment of fresh nuclear fuel imported from Russia has reached the Rooppur Nuclear Power Plant project site in Bangladesh. The arrival completes the scheduled fuel deliveries in nine consignments for the plant's two units.

However, completion of fuel deliveries does not mean that both units have begun commercial operation. Further technical testing, safety verification and regulatory approvals are required before the plant can operate at full capacity.

The uranium-carrying convoy entered the under-construction nuclear power plant in Pakshi Union of Ishwardi Upazila, Pabna, at 5:48 am on Friday, November 27.

The convoy, consisting of three trucks escorted by the Bangladesh Army, travelled along the Natore-Kushtia-Pabna highway and crossed the Dashuria traffic intersection, a major gateway to the northern and southern regions.

Officials, including Russian nationals working at the project, welcomed the convoy upon its arrival.

Final Shipment Arrives Under Tight Security

A special security cordon involving the Bangladesh Army and other law enforcement agencies was maintained along the highway to ensure the safe and uninterrupted movement of the uranium shipment.

For security reasons, the movement of small and large vehicles along the Pabna-Natore-Kushtia highway was suspended from 5:30 am to 6:00 am.

Traffic returned to normal after the shipment reached the project site.

Ishwardi Police Station Officer-in-Charge Ashadur Rahman Asad told Banglanews that Pabna district police and other law enforcement personnel had established a special security cordon to ensure that the uranium-carrying vehicles arriving from Dhaka could reach the project site without traffic congestion.

A Total of 211 Fuel Assemblies

According to project-related information, two additional fuel shipments were brought for Unit One, while seven shipments were delivered for Unit Two.

Under the plan of Russia's state nuclear corporation Rosatom, 163 uranium fuel assemblies were scheduled to be delivered for Unit Two in seven cargo aircraft.

Another 48 assemblies were planned for Unit One's refuelling requirements, to be transported in two cargo aircraft.

The arrival of the final shipment completes the planned fuel transportation process. The two units were scheduled to receive a total of 211 uranium fuel assemblies.

Two VVER-1200 Units

Built using Russian technology, the Rooppur Nuclear Power Plant consists of two VVER-1200 reactor units.

Each unit has a generation capacity of 1,200 megawatts.

Once both units are fully operational, the plant will be capable of supplying a combined 2,400 megawatts of electricity to the national grid.

Achieving this capacity will depend on the successful completion of testing, commissioning, safety verification and regulatory approval for commercial operation.

Unit One Continues Trial Electricity Supply

Alongside the completion of fuel imports, trial electricity supply from the plant's first unit is progressing.

The second trial supply to the national grid began at 10:20 am on November 23.

At this stage, the plant was scheduled to conduct a test supplying 300–350 megawatts of electricity for a period of 10 to 24 hours.

Earlier, Unit One was connected to the national grid for the first time at 3:16 pm on November 17.

After generating electricity continuously for more than eight and a half hours, production was temporarily halted at 11:50 pm.

The first test recorded a maximum generation output of 375 megawatts.

Commercial Operation After Trial Period

Project Director Dr Md. Kabir Hossain told that the second phase of trial electricity supply from Unit One began at 10:20 am on November 23.

He said the test would involve supplying 300–350 megawatts of electricity to the national grid for 10 to 24 hours.

Under the agreement with the Russian contractor, Unit One is expected to begin phased commercial electricity supply at full capacity after a 10-month trial operation period.

During this period, the Bangladesh Atomic Energy Commission will take over responsibility for Unit One from the Russian contractor through a provisional takeover process.

Subsequently, Nuclear Power Plant Company Bangladesh Limited (NPCBL) will begin operating as the plant's operating organisation following a government gazette notification.

Bangladesh's Progress in Nuclear Power

Science and Technology Minister Fakir Mahbub Anam told that Bangladesh had emerged as the world's 33rd nuclear-powered country through the successful test, describing it as a moment of great national pride.

He said electricity generated by the country's first nuclear power plant had been connected to the national grid on a trial basis after a long period of anticipation, continuous technical work and complex testing at different stages.

The completion of fuel deliveries and the ongoing trial electricity supply from Unit One mark important progress in Bangladesh's nuclear power programme.

However, the plant must complete the remaining technical and regulatory stages before moving towards full commercial generation.