Power Supply to National Grid

Rooppur Begins Second Grid Transmission

  • Second trial transmission started Monday at 10:20 AM.
  • Supplying 300-350 MW for 10 to 24 hours.
  • First 350 MW trial run occurred on November 17.

Rooppur Begins Second Grid Transmission
Nov 23, 2026 11:28

The Rooppur Nuclear Power Plant (RNPP) commenced its second phase of trial electricity transmission to the national grid at 10:20 AM on Monday (November 23, 2026).

The development was confirmed in a press release issued by Saikat Ahmed, Senior Scientific Information Officer and Media Focal Point of the Rooppur Nuclear Power Plant Construction Project.

Quoting Project Director Dr. Md. Kabir Hossain, the statement noted that approximately 300 to 350 megawatts (MW) of electricity is being supplied to the national grid during this phase. The trial transmission will continue for 10 to 24 hours, during which essential technical evaluations of the plant’s generation systems and integrated grid synchronization will be conducted.

Earlier, on November 17, 2026, at 3:16 PM, the plant successfully initiated its maiden trial transmission of roughly 350 MW of electricity into the national grid. Today's grid connection marks the second consecutive phase in the ongoing commissioning process.

Successful completion of these trial runs will bring Bangladesh closer to regular, commercial-scale nuclear power generation and distribution.