Technical and signaling installations underway

Metro rail to Kamalapur opens July 2027

  • Regular passenger service to Kamalapur begins in July 2027
  • Adding 1.16 km will expand route to 17 stations
  • Civil works reached 84.85 percent; electro-mechanical 58 percent complete

Metro rail to Kamalapur opens July 2027
Nov 22, 2026 09:31

Expanding modern rapid transit infrastructure and automated rail signaling systems, the extension of Dhaka's Uttara-Motijheel metro rail line up to Kamalapur is progressing steadily. According to relevant sources, following multiple schedule revisions due to earlier construction delays, regular passenger operations on the Motijheel-Kamalapur section are now targeted to commence in July 2027.

According to data from the Dhaka Mass Transit Company Limited (DMTCL), the currently operational stretch of MRT Line-6 spans 20.10 kilometers. With the addition of the new 1.16-kilometer section, the total route length will reach 21.26 kilometers, encompassing 17 stations. As of September 30, 84.85 percent of civil works and 58 percent of electrical and mechanical works on the extended section have been completed.

Relevant sources indicate that the primary physical infrastructure is scheduled to be erected before December 31 this year. Viaduct construction has already been completed and handed over to the contractor for rail track installation. Additionally, the main structure of Kamalapur station has been built, with interior finishing, electro-mechanical equipment installation, and entry-exit pathways currently underway. Architectural and associated works are targeted for completion by December 31, 2026.

However, completing physical structures alone is insufficient to begin passenger operations. Prior to launch, rail tracks, power supply, automated signaling systems, automatic fare collection (AFC), platform safety systems, telecommunications, lifts, and escalators must be fully commissioned. Subsequently, integrated system testing and trial runs will be conducted to verify comprehensive operational safety, which will ultimately determine the final launch timeline. Notably, the opening of this stretch was previously projected for January 1, 2027, and later April-May 2027, before being rescheduled to July 2027.