Bangladesh emerges as 33rd nuclear power nation
Commercial production set to begin after a 10-month trial operation
- First unit begins trial supply of 350 MW electricity to the national grid
- Bangladesh officially becomes the 33rd nuclear power-producing nation globally
Marking a historic milestone in Bangladesh’s power and energy sector, the Rooppur Nuclear Power Plant has successfully synchronized with the national grid and initiated trial electricity supply. On Tuesday, November 17, 2026, at 3:00 PM in Ishwardi, Pabna, sources informed that the first unit began supplying 350 MW of electricity to the national grid for the first time in the presence of Science and Technology Minister Fakir Mahbub Anam.
Speaking to journalists following the connection, Science and Technology Minister Fakir Mahbub Anam said, “Through this successful test, Bangladesh has emerged as the 33rd nuclear power-producing nation in the world, which is joyful news for the entire nation. The connection of electricity from the Rooppur Nuclear Power Plant to the national grid is an important milestone for the country's power and energy sector. A long-cherished expectation has begun to turn into reality, and scientists, engineers, officers, and employees all contributed to this achievement.” The Minister further noted that up to 350 MW of electricity was supplied experimentally to the grid with highly satisfactory results, and it was subsequently stabilized at 300 MW to maintain grid stability.
Regarding observations from the International Atomic Energy Agency (IAEA), the Minister said, “The agency's delegation is highly satisfied after reviewing the overall progress, preparation, and safety measures of the project, which is why today's successful grid synchronization test became possible.” He also mentioned that Prime Minister Tarique Rahman extended heartfelt congratulations to everyone involved in this remarkable success and expressed gratitude to the project team and the general public.
The briefing was attended by the Prime Minister’s Adviser on Science and Technology Rehan Asif Asad, Science and Technology Secretary Md. Anwar Hossain, Rooppur Nuclear Power Plant Construction Project Director Dr. Md. Kabir Hossain, and Managing Director of Nuclear Power Plant Company Bangladesh Limited (NPCBL) Dr. Jahedul Hasan, among other senior officials.
Project Director Dr. Md. Kabir Hossain stated that according to the schedule, electricity generated under the initial trial connection will be supplied to the national grid for about 8 to 10 hours to evaluate the performance and stability of the turbines, generators, and integrated grid management. Afterward, the plant will be disconnected for technical inspections and reconnected for 4 to 6 hours following a 28-hour break for further operational testing.
Dr. Kabir Hossain added that once all technical evaluations yield satisfactory results, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required for the next phase of trial operation. Following BAERA's clearance and a 10-month trial operation as per the agreement with the Russian contractor, the first unit will commence permanent commercial supply at full capacity, leading to a provisional takeover by the Bangladesh Atomic Energy Commission and subsequent operation by NPCBL via government gazette. With two units of 1,200 MW each, the 2,400 MW plant is expected to significantly bolster national energy security and meet growing electricity demands.