Bangladesh Enters Nuclear Power Testing Era

Rooppur Connects 350MW to National Grid

  • Bangladesh's first nuclear electricity enters the national grid.
  • Initial experimental supply starts at 350 megawatts.
  • Ten-month trial operation precedes commercial generation.

Rooppur Connects 350MW to National Grid
Nov 17, 2026 15:34

Bangladesh has taken a significant step towards realizing its long-awaited nuclear power ambitions, as electricity generated at the country's first nuclear power plant in Rooppur was connected to the national grid on a trial basis for the first time on Tuesday.

The experimental supply began at 3:16 pm, with an initial 350 megawatts of electricity from the plant's first unit entering the national grid.

Saikat Ahmed, senior information officer of the Bangladesh Atomic Energy Commission, confirmed the country's first experimental integration of nuclear-generated electricity into the national grid.

According to project sources, the initial phase of the First Grid Connection (FGC) is planned to supply electricity to the national grid for approximately eight to 10 hours. During this period, engineers will closely monitor the performance and stability of the plant's turbine, generator and integrated operational systems in coordination with the national grid.

Following the initial test, the plant will be disconnected from the grid for further technical assessments. After an interval of approximately 28 hours, it is scheduled to be reconnected for another four to six hours to complete the subsequent tests.

Each stage will assess the performance of different plant systems, turbine and generator operations, and the compatibility of electricity supply with the national grid.

Generation capacity will be increased gradually in accordance with International Atomic Energy Agency (IAEA) guidelines and international nuclear safety standards. The first unit is expected to reach 100 per cent capacity through successive tests, licensing procedures and regulatory approvals.
The historic grid connection took place in the presence of Science and Technology Minister Fakir Mahbub Anam

Among those present were Science and Technology Secretary Md. Anwar Hossain; Bangladesh Atomic Energy Commission Chairman (acting) Dr. M. Moinul Islam; BAERA Chairman Mahmudul Hasan; NPCBL Managing Director Dr. Jahedul Hasan; Project Director Dr. Md. Kabir Hossain; and other engineers, scientists and officials involved in the project.


The Rooppur Nuclear Power Plant is being developed with two generating units, each with a capacity of 1,200 megawatts. Once both units become operational, the facility will have a combined generation capacity of 2,400 megawatts.

The first experimental supply of nuclear-generated electricity to the national grid marks a major milestone in Bangladesh's efforts to diversify its energy mix through nuclear power.