First reactor nears grid connection
Rooppur May Begin Grid Supply This Week
- Trial electricity supply from the first unit is being prepared
- The unit may supply 300 MW to the grid in November
- Full-capacity supply may take another five to six months
Bangladesh is approaching a major milestone in its adoption of nuclear power technology, as electricity from the first unit of the Rooppur Nuclear Power Plant may enter the national grid on a trial basis this week. If technical preparations proceed successfully and the Bangladesh Atomic Energy Regulatory Authority (BAERA) grants approval, the unit could begin supplying 300 megawatts (MW) of electricity to the grid in November. However, achieving full electricity supply capacity from the first unit may take another five to six months.
Multiple sources familiar with the project said preparations are underway to connect electricity from the country's first nuclear power plant to the national grid on a trial basis this week. The process could proceed as planned unless technical or other problems, or an unexpected crisis, arise. This would mark the beginning of nuclear electricity supply from Rooppur to the national grid.
The sources said preparations for trial generation at the first unit are progressing. Initial activities are advancing successfully, while coordination among different technical systems is underway. When the reactor reaches 40 percent of its thermal capacity, it will be possible to generate approximately 30 to 35 percent of its full electricity output. At this stage, around 300 MW could potentially be supplied to the national grid in November.
The entire process will be closely monitored after electricity is connected to the grid. Generation and supply operations will be observed for several days to identify and rule out any technical faults. If everything proceeds smoothly, approval from BAERA will be required at this stage. Following regulatory approval, a formal inauguration of the 300 MW electricity supply may take place.
Prime Minister Tarique Rahman may attend the inauguration as the chief guest. Russian President Vladimir Putin may also join the event through a video conference, according to relevant sources. However, the date of the ceremony has not yet been finalised. December is being considered for the inauguration, taking into account the possible participation of the prime minister and the Russian president.
Commenting on the development, BAERA Chairman Mahmudul Hasan said it was too early to confirm when electricity supply to the national grid would begin. Efforts were underway to start operations as soon as possible.
He said that after the trial supply begins, every stage of electricity generation and delivery will be examined to ensure that all systems are functioning properly. The formal inauguration will take place only after authorities are satisfied that there are no problems.
Mahmudul Hasan also said the ceremony's schedule would depend on when the prime minister would be available. This is another reason why the formal inauguration date cannot yet be confirmed.
Relevant sources further said electricity generation and supply from the first unit would be increased gradually after the initial 300 MW is connected to the national grid. It could take another five to six months to reach full capacity and supply the entire output to the grid.
Accordingly, although the formal inauguration of the initial 300 MW supply may take place this year, the first unit could reach full-capacity grid supply between April and June next year.
Built in Ishwardi, Pabna, the Rooppur Nuclear Power Plant has been developed with Russia's advanced technology, financial and technical assistance, and supervision. The project is being implemented by Atomstroyexport, the engineering division of Russia's state-owned nuclear energy corporation Rosatom.
The power plant has two units, each with a generation capacity of 1,200 MW. Once both units become operational, the facility will have a combined electricity generation capacity of 2,400 MW.
//DBTech/IH/SCDRE/FOED//