Test Run Paused After 8.5 Hours of Power Supply

Rooppur Unit Disconnected From Grid

  • Rooppur's first unit disconnected after test run
  • Peak production reached 375 MW during initial trial
  • Second phase of grid testing planned after 28-hour break

Rooppur Unit Disconnected From Grid
Nov 18, 2026 20:12

The first unit of the Rooppur Nuclear Power Plant has been temporarily disconnected from the national grid following approximately eight and a half hours of experimental power supply. The electricity supply from the first unit was halted at 11:50 PM on Tuesday (November 17).

During this initial phase of testing, the unit's power generation peaked at 375 megawatts. Authorities stated that the disconnection was implemented to prepare for the next phase of technical evaluations.

Earlier on Tuesday, nuclear electricity was integrated into the national grid for the first time at 3:16 PM. Twenty-nine minutes later at 3:45 PM, production in the first unit reached 350 MW.

To maintain grid stability, production was initially stabilized at 300 MW before being ramped up to 375 MW. Dr. Zahedul Hasan, Managing Director of Nuclear Power Plant Company Bangladesh Limited (NPCBL), confirmed these details.

He explained that prior to connecting the generator to the grid, harmony in voltage, frequency, and other electrical characteristics between both systems was verified. Tuesday's connection marked the beginning of assessing how stably the plant's machinery and control systems operate alongside the national grid via synchronization. Following about eight and a half hours of power transmission, the operational effectiveness of the turbines, generators, and integrated grid systems was evaluated.

Dr. Hasan added that after a roughly 28-hour recess, a second testing phase involving a four-to-six-hour grid reconnection is planned. //DBTech/RKS/SME/MIST//